General Service <50 kW Electricity Rates

Your electricity bill is made up of delivery charges, distribution charges, regulatory charges and electricity charges. All but the distribution charges are collected on behalf of other parties. Kitchener-Wilmot Hydro retains only the distribution charges.


Choosing your pricing plan

If you are a residential or small business customer that pays time-of-use (TOU) electricity prices, starting October 13, 2020, you can choose to switch to Tiered prices for billing periods that begin as early as November 1, 2020.

Below are the current electricity rates for small business customers.


Electricity Charges

The electricity charge of your bill is calculated using rates which are determined by the Ontario Energy Board. The most recent rates are listed in the table below.


For customers paying time-of-use rates: 

COVID-19 Recovery Rate - Ends October 31, 2020.

Time-of-use and tiered pricing take effect November 1, 2020.

From June 1, 2020 until October 31, 2020, customers paying time-of-use electricity rates paid the COVID-19 Recovery Rate, which was a fixed rate of 12.8 cents per kilowatt hour for electricity 24 hours a day, 7 days a week. 

For more information about the COVID-19 Recovery Rate, read the Government’s news release.

COVID-19 Recovery Rate from June 1, 2020 through October 31, 2020
Electricity consumed June 1, 2020 through October 31, 2020 12.8ȼ / kWh

Time-of-use Pricing

For electricity consumed between November 1, 2020 and December 31, 2020:

Time-of-Use Periods - Winter

Period

Time

Cost

Off-peak

Weekdays 7 pm to 7 am

Weekends & Holidays - all Day

10.5ȼkWh

Mid-peak

Weekdays 11 am to 5 pm 

15.0ȼ/kWh

On-peak

Weekdays 7 am to 11 am and 5 pm to 7 pm

21.7ȼ/kWh 

Provincewide Shutdown Rate

January 1 - February 22, 2021

24 hours a day, 7 days a week

8.5ȼ/kWh

For electricity consumed starting February 23, 2021, time-of-use rates set effective January 1, 2021 apply.


 

Time-of-use rates effective January 1, 2021
PeriodTimeCost
Off-peak

Weekdays 7 pm to 7 am

Weekends & Holidays - all Day

8.5 ȼkWh
Mid-peak Weekdays 11 am to 5 pm 11.9 ȼkWh
On-peak Weekdays 7 am to 11 am and 5 pm to 7 pm 17.6 ȼkWh

Note: Time-of-use rates effective January 1, 2021 were replaced with the special shutdown rate of 8.5 ȼkWh on electricity consumption between January 1, 2021 and February 22, 2021. Regular time-of-use rates resume starting February 23, 2021. 


 

Tiered Regulated Price Plan Rates

Note: The special shutdown rate of 8.5 cents per kilowatt hour ended February 22, 2021. Tired rates set January 1, 2021 apply starting February 23, 2021. 

If your business is not on time-of-use pricing, the tiered Regulated Price Plan (RPP) pricing is listed below.

For consumption from November 1, 2019 until October 31, 2020:

  • First 750 kWh/month: 11.9ȼ/kWh
  • Remaining kWh/month: 13.9ȼ/kWh
For consumption November 1 - December 31, 2020
First 750 kWh/month 12.6 ȼkWh
For electricity used above 750 kWh/month 14.6 ȼkWh

Provincewide Shutdown Rate for consumption from January 1 - February 22, 2021

8.5 ȼkWh
Tiered rates effective January 1, 2021
First 750 kWh/month10.1 ȼkWh
For electricity used above 750 kWh/ month 11.8 ȼkWh

Note: Tiered rates effective January 1, 2021 were replaced with the special shutdown rate of 8.5 ȼkWh on electricity consumption between January 1, 2021 and February 22, 2021. Regular tiered rates resume starting February 23, 2021.

Back to top


Ontario Electricity Rebate

Effective November 1, 2019 the Government of Ontario introduced a new electricity rebate called the Ontario Electricity Rebate (OER). The OER is an on-bill rebate for households, multi-unit complexes, farms, long-term care homes, and many small businesses.

Between November 1, 2019 and October 31, 2020, the OER rebate was 31.8%.

Between November 1 and December 31, 2020, the OER rebate was 33.2%.

Effective January 1, 2021, the OER rebate has been reduced to 21.2%.

For more information about the OER, please visit https://www.ontario.ca/page/changes-your-electricity-bill

Back to top


Delivery Charges

These charges are set by Kitchener-Wilmot Hydro and are approved by the Ontario Energy Board to cover the cost of maintaining the highly efficient electricity distribution system in Kitchener and Wilmot Township, including 24/7 emergency services, infrastructure such as poles, wires, meters, transformers, substations, and our local customer service centre. Kitchener-Wilmot Hydro has one of the lowest delivery charges in the province.

Below are our delivery and service charges for small businesses between January 1, 2020 and December 31, 2020. 

Delivery Charges

Cost

per 

Transmission Network Charge

$0.0055

 kWh

Transmission Connection Charge

$0.0015

 kWh

Smart Metering Entity Charge

$0.5700

 Month

Distribution Charge (time-of-use customers)

 $0.0141

 kWh

Distribution Charge (retailer customers)

$0.0118

kWh

Distribution Service Charge

$27.51

 Month

Below are our delivery and service charges for small businesses effective January 1, 2021. 

Delivery Charges

Cost

per 

Transmission Network Charge

$0.0054

 kWh

Transmission Connection Charge

$0.0015

 kWh

Smart Metering Entity Charge

$0.5700

 Month

Distribution Charge (TOU & Tiered customers)

 $0.0143

 kWh

Distribution Charge (retailer customers)

$0.0157

kWh

Distribution Service Charge

$28.07

 Month

 


Regulatory Charges

Regulatory Charges

Cost

per 

Standard Supply Administration Charge

$0.25

Month

Wholesale Market Charge

$0.0039

 kWh

Loss Adjustment

Some electricity is lost along the lines on its way to your business. Some electricity charges and transmission charges may be subject to loss adjustment factors. These are known as "line losses." 


Electricity Retailers

Customers who have a contract with a retailer will be billed the electricity rates agreed to in the terms and conditions of the contract they have signed, which may be different than the time-of-use rates set by the province because they do not include global adjustment charges. Kitchener-Wilmot Hydro is not a party to these contracts and only invoices the amount as directed by the retailer. Learn more about your rights when it comes to electricity contracts.


Specific Service Charges

Outside of electricity consumption charges, customers may be subject to other service charges, as follows:

Customer Administration

Service Charge
Returned cheque ($15.00 plus bank charges of $7.00) $22.00
Account set up charge/change of occupancy charge (plus credit agency costs if applicable) $20.00
Meter dispute charge, plus Measurement Canada fees (if meter found correct) $30.00

Non-Payment of Account

Service Charge
Late payment - per month 1.50%
Reconnection at meter - during regular business hours $65.00
Reconnection at meter - after regular business hours $185.00
Reconnection - during regular business hours $95.00

Other

Service Charge
Meter removal without authorization $355.00
Service call - after regular business hours $105.00

Back to top


Definitions and Explanations of Charges

Electricity Charges

Electricity use is billed in kilowatt hours (kWh), which is a measure of energy used over time. For example, if you use a 1,000 watt microwave for one hour, you used 1,000 watt-hours – or one kWh.

Time-of-use (TOU) rates

With time-of-use rates, you pay for electricity based on when you use electricity in each of the three time-of-use periods: on-peak, mid-peak, and off-peak. Time-of-use rates are set twice each year by the Ontario Energy Board, on May 1 and November 1. Electricity charges are collected by Kitchener-Wilmot Hydro and paid directly to electricity suppliers. Kitchener-Wilmot Hydro does not keep any of these charges.

Time-of-use rates are based on provincial demand for electricity.

  • On-peak pricing is highest because that is when provincial demand for electricity is highest.
  • Off-peak pricing is lowest because that is when provincial demand for electricity is lowest.

Provincial "peak" electricity use changes in summer and winter.

  • In summer, provincial electricity use is typically highest in the middle of the day, when air conditioners are working hardest.
  • In winter, provincial electricity use is typically highest at the beginning of the day, when people and businesses are waking up and turning on lights, appliances, and machinery, and at the end of the day, when families return home and turn on lights and appliances for the evening.

For more information about time-of-use pricing, visit the Ontario Energy Board website

Tiered Rates

With Tiered prices, you can use a certain amount of electricity each month at a lower price. Once that limit (called a threshold) is exceeded, a higher price applies. 

For small business customers, the Tier threshold is 750 kWh all year round.

Tiered prices give you the flexibility to use electricity at any time of day at the same price, although that price will change if you exceed the threshold during the month.

For more information about Tiered Regulated Price Plan rates, please visit the Ontario Energy Board website.

Back to charges


Delivery Charges

Delivery is the cost of bringing electricity from generation stations to your home or business. Kitchener-Wilmot Hydro’s distribution charges are included in this portion of your bill.

Electricity Usage Adjustment Factor

  • An energy adjustment applied to the total amount of electricity used during the billing period to account for the line losses in the electricity system that are not measured by your meter. When electricity is delivered over a power line, it is normal for a small amount of power to be lost as heat. Line losses are an unavoidable part of delivering electricity. The adjustment factor is approved by the Ontario Energy Board and is reviewed regularly as part of the rate setting process.

Distribution Service Charge

  • This is a fixed or variable monthly charge that covers the costs associated with meter reading, billing, customer service, account maintenance, and general utility operations. 

Transmission Connection

  • The transmission connection charge covers the cost of connecting Kitchener-Wilmot Hydro’s distribution system to Hydro One’s transmission lines, as well as the cost of transforming electricity from high transmission voltages to lower voltages for distribution. This charge is applied against your total energy in kWh.

Transmission Network Charge

  • The transmission network charge covers the cost of delivering the electricity from the generating stations to the region through Hydro One’s transmission system. This charge is collected on behalf of Hydro One. This charge is applied against your total energy in kWh.

Smart Meter Entity

  • The charge paid to cover the cost of services provided by the Independent Electricity System Operator (IESO) for the implementation and operation of the province’s Meter Data Management/Repository, which stores, validates and manages hourly electricity information transmitted by smart meters.

Back to Delivery Charges


Energy Charges

Energy charges are made up of the sum of on-peak, mid-peak, and off-peak measured energy in kWh multiplied by the applicable time-of-use rate. Electricity charges are collected by Kitchener-Wilmot Hydro and paid directly to electricity suppliers. Kitchener-Wilmot Hydro does not keep any of these charges.

Back to top


Regulatory Charges

Regulatory charges include the cost of services required to operate the electricity system and run the wholesale electricity market. The Ontario Energy Board sets these charges.

Wholesale Market Service

  • The wholesale market service charge covers the cost of services provided by the IESO to operate the wholesale electricity market and maintain the reliability of the high voltage power grid and certain costs incurred by local utilities to connect renewable generation.

Standard Supply Administration Charge

  • The standard supply administration charge covers a portion of a utility’s administrative costs to provide electricity bills to customers that receive an invoice directly from the utility (i.e. customers that are not billed by a retailer). This charge is set by the Ontario Energy Board and is the same for all utilities across the province.

Go back to regulatory charges


Global Adjustment

Global adjustment (GA) covers the cost of building new electricity infrastructure in the province, as well as delivering Ontario's conservation programs. It is calculated by the IESO and embedded in the time-of-use rates on your bill. If you have a contract with an energy retailer, you are billed global adjustment in addition to your energy costs. GA is calculated each month and is billed on your total kilowatt hour use. Learn more about how the GA is calculated